2018SEMIANNUAL REPORT

CONSTRUCTION PROGRESS

2018 SEMIANNUAL HIGHLIGHTS:

  • Project was completed and opened to traffic.
  • A ribbon cutting ceremony was held in May 2018 to mark the official opening of the project corridor.
  • Stamped crosswalks were added to the scope of the project and were completed in May 2018.

PUBLIC OUTREACH

Ribbon Cutting Ceremony

May 2018

30 ATTENDEES = 10
Community Meetings

Three open houses were held to share construction updates

149 TOTAL ATTENDEES = 10
Business Meetings

The project team held two meetings open to local businesses to discuss potential impacts.

17 TOTAL ATTENDEES = 10
Online Meetings

Online meetings were launched to complement in-person meetings.

457 ATTENDEES = 10
Resident mailings
10,457 TOTAL SENT = 100
Business mailings
98 TOTAL HAND DELIVERED = 100

PROGRESS

Initial pavement repairs on Folly Road

2070SQUARE YARDS OF FULL DEPTH PATCHING

Feet of bike lanes added

4100COMPLETE OF 4,100 FT

Feet of sidewalks added

7200COMPLETE OF 7,200 FT

Feet of drainage pipe

7000COMPLETE OF 7,000 FT

Additional turn lanes added

7COMPLETE OF 7

Dual left turn lanes

1COMPLETE OF 1

Tons of pavement laid

16544TONS PLACED

Utilities relocated

100%COMPLETE

Traffic and pedestrian signals updated

100%COMPLETE

SCHEDULE

Phase 1

100% Complete

Phase 2

100% Complete

Phase 3

100% Complete

Phase 4

100% Complete

Phase 5

100% Complete

FINANCIAL

Disadvantaged Business Enterprise Participation

116% OF GOAL COMPLETED 15.7% of contract
Mandatory 13.5% of total construction contract; Mandatory 13.5% required due to federal funding rules

Small Business Enterprise Participation

6.3% OF TOTAL CONSTRUCTION CONTRACT
Mandatory SBE% is not allowed due to federal funding rules

$ Spent

$12.3M